Myrtle School Road

 

MSConstr-1

What's Happened?                   Council awarded the contract to Triangle Grading and Paving. Work began November 3, 2014. Underground utility work is expected to be complete by the end of the year.

MSConstr-3

Current Status:                     May 2017: Work is 90% complete. City expects Substantial competion by May 31. Project close out June 2017.

MSConstr-4

Look ahead:                             City expects substantial competition by May 31. Project close out June 2017.

MSConstr-11

Project Contacts:                     City of Gastonia Engineering 150 S. York Street Gastonia NC 28052 (704)866-6943 Please reference the project name when you call.

Project Description:

This Project will widen S. Myrtle School Road to three lanes from Franklin Blvd to Hudson Blvd to accommodate two travel lanes and a turn lane. Sidewalk, curb, and gutter will be constructed on both sides of S. Myrtle School Road. There will be utility relocations above and below ground to accommodate the widening.