A site plan is needed for any new building construction or addition to commercial, industrial, condominium, or apartment complexes/developments. See contact below for other conditions that may apply.
The site plan process is:
- Pick up appropriate checklist from Customer Service Representative
- Submit six (6) copies of plan for review
- Technical Review Committee (TRC) reviews plan-every Monday afternoon
- Comments returned to engineer for corrections-approximately three (3) weeks after submittal
- Approval of site plan
- Building permit
- Approximate total approval time is two (2) months
- Submittal of building plans can be concurrent with site plan submittal
*Note: Plans must be submitted before 12:00 Monday to make that week's TRC meeting