Project Description: The existing storm drain system is undersized and comprised of mostly corrugated metal pipe. The proposed project will replace the existing system with RCP.
Current Status: Notice to Proceed was issued to Kennedy Concrete and Utilities on May 8, 2017. Construction is expected to take about 4 months.
STREET CLOSURE: May 25, 2017. Third Ave from S. South to S. Marietta. Street will be Icose for approximately 65 days.
![]() ![]() ![]() ![]() ![]() |